The project comprised over 200 lines amounting to 500 piping Isometrics coming from the digesters and the Central Processing Facility. The considerations for each included Insulation, Heat Tracing Requirements, Pipe Support Standards, and Piping Specification among a host of other standards and specifications.
Given the importance of a quick turnaround, a two-shift team was put in place, where the second shift would begin with evaluations with the customer. Taking advantage of the time-zone difference, the Enventure teams were able to perform the rerouting and rework tasks and ready them for review before the beginning of the next US day.